Azucarera event hall – External structure, UPN sections for the gable-end and access ramp

Company / Location:

La Azucarera

Details:

This project was carried out in several phases.

  • Phase 1: Fabrication of 8 trusses and the external steel structure, including the beams, at
    Castillón Martínez’s facilities. Subsequently, the trusses, measuring 24 metres in length
    and 6 metres in width, were transported by special haulage from Castillón Martínez to
    the Sugar Factory building.
  • Phase 2: Reinforcement of the first-floor concrete slab with steel columns and beams.
  • Phase 3: Installation of columns for the extension of the building.
  • Phase 4: Installation of portal frames between the Sugar Factory building and the Nativity Scene building to extend the facility. Several 15-metre compact crawler lifts were required to carry out the on-site welding work, with the assistance of an 80-tonne mobile crane.
  • Phase 5: Installation of guardrails around the entire perimeter.
  • Phase 6: Installation of the structural framework for the south atrium façade (park side).
  • Phase 7: Installation of trusses and purlins for the new roof.
  • Phase 8: Installation of a vehicle access ramp on the north side (supermarket area).

Thanks to our specialised team and extensive industry experience, we successfully met the demanding quality standards required for this project.